Construction Timeline Updates 2019

Site Construction
Task Start Date Planned Completion Date
Cleaning and Grubbing 11-Sep-15 Complete
Site Grading 1-Oct-15 Complete
Building Pad 15-Oct-15 Complete
Environmental 1-Oct-15 Complete
Erosion Control 15-Oct-15 Complete
Site Utilities 10-Apr-17 Complete
Drainage 1-Dec-15 Complete
Feeder Drainage 15-May-17 Complete
Granite Ganesha Garbhagraham
Task Start Date Planned Completion Date
Ganesha Garbhagraham – Granite purchase Sep-15 Complete
Granite Garbhagraham work in India Jan-16 Complete
Concrete
Task Start Date Planned Completion Date
Building Piers 1-Mar-16 Complete
Grade Beams 7-Jul-16 Complete
Building Slab 20-Jan-17 Complete
Fire Lanes and Driveways 3-Apr-17 Complete
Masonry
Task Start Date Planned Completion Date
Split face CMU Blocks 1-Dec-17 5-Apr-19
Metals
Task Start Date Planned Completion Date
Structural Steel 1-Dec-18 30-Apr-19
Trusses and Decking 15-Jan-19 10-May-19
Hand rails and fencing 1-Dec-18 30-Jun-19
Thermal and Moisture Protection
Task Start Date Planned Completion Date
Wall Insulation 1-Feb-19 30-Apr-19
Roof Insulation 1-Feb-19 15-May-19
TPO Roofing 1-Feb-19 31-May-19
Doors and Windows
Task Start Date Planned Completion Date
Accordion Doors 1-Apr-19 30-Jun-19
Exterior and Interior windows 1-Jul-18 31-May-19
Finishes
Task Start Date Planned Completion Date
Acoustical Ceiling 15-Apr-19 15-Jun-19
Tape bed fixtures and Paint 30-Apr-19 30-Jun-19
Mechanical and Plumbing HVAC
Task Start Date Planned Completion Date
HVAC 10-Jan-19 31-May-19
Metal duct system 10-Jan-19 31-May-19
Kitchen vent hood 5-Mar-19 31-May-19
Plumbing Rough 3-Oct-16 15-Feb-17
Plumbing Top 15-Apr-19 30-May-19
Grease Trap 4-Jan-17 20-Apr-17
Electrical
Task Start Date Planned Completion Date
Electrical Panel 1-Sep-18 20-Apr-19
Electrical Service 1-Apr-19 28-Apr-19
Electrical Rough 1-Feb-18 21-Dec-18
Electrical Top 15-Apr-19 1-Jun-19
Irrigation
Task Start Date Planned Completion Date
Sprinkler 20-Apr-19 15-Jun-19
Landscape 20-Apr-19 30-Jun-19