Site Construction | ||
Task | Start Date | Planned Completion Date |
---|---|---|
Cleaning and Grubbing | 11-Sep-15 | Complete |
Site Grading | 1-Oct-15 | Complete |
Building Pad | 15-Oct-15 | Complete |
Environmental | 1-Oct-15 | Complete |
Erosion Control | 15-Oct-15 | Complete |
Site Utilities | 10-Apr-17 | Complete |
Drainage | 1-Dec-15 | Complete |
Feeder Drainage | 15-May-17 | Complete |
Granite Ganesha Garbhagraham | ||
Task | Start Date | Planned Completion Date |
---|---|---|
Ganesha Garbhagraham – Granite purchase | Sep-15 | Complete |
Granite Garbhagraham work in India | Jan-16 | Complete |
Concrete | ||
Task | Start Date | Planned Completion Date |
---|---|---|
Building Piers | 1-Mar-16 | Complete |
Grade Beams | 7-Jul-16 | Complete |
Building Slab | 20-Jan-17 | Complete |
Fire Lanes and Driveways | 3-Apr-17 | Complete |
Masonry | ||
Task | Start Date | Planned Completion Date |
---|---|---|
Split face CMU Blocks | 1-Dec-17 | 5-Apr-19 |
Metals | ||
Task | Start Date | Planned Completion Date |
---|---|---|
Structural Steel | 1-Dec-18 | 30-Apr-19 |
Trusses and Decking | 15-Jan-19 | 10-May-19 |
Hand rails and fencing | 1-Dec-18 | 30-Jun-19 |
Thermal and Moisture Protection | ||
Task | Start Date | Planned Completion Date |
---|---|---|
Wall Insulation | 1-Feb-19 | 30-Apr-19 |
Roof Insulation | 1-Feb-19 | 15-May-19 |
TPO Roofing | 1-Feb-19 | 31-May-19 |
Doors and Windows | ||
Task | Start Date | Planned Completion Date |
---|---|---|
Accordion Doors | 1-Apr-19 | 30-Jun-19 |
Exterior and Interior windows | 1-Jul-18 | 31-May-19 |
Finishes | ||
Task | Start Date | Planned Completion Date |
---|---|---|
Acoustical Ceiling | 15-Apr-19 | 15-Jun-19 |
Tape bed fixtures and Paint | 30-Apr-19 | 30-Jun-19 |
Mechanical and Plumbing HVAC | ||
Task | Start Date | Planned Completion Date |
---|---|---|
HVAC | 10-Jan-19 | 31-May-19 |
Metal duct system | 10-Jan-19 | 31-May-19 |
Kitchen vent hood | 5-Mar-19 | 31-May-19 |
Plumbing Rough | 3-Oct-16 | 15-Feb-17 |
Plumbing Top | 15-Apr-19 | 30-May-19 |
Grease Trap | 4-Jan-17 | 20-Apr-17 |
Electrical | ||
Task | Start Date | Planned Completion Date |
---|---|---|
Electrical Panel | 1-Sep-18 | 20-Apr-19 |
Electrical Service | 1-Apr-19 | 28-Apr-19 |
Electrical Rough | 1-Feb-18 | 21-Dec-18 |
Electrical Top | 15-Apr-19 | 1-Jun-19 |
Irrigation | ||
Task | Start Date | Planned Completion Date |
---|---|---|
Sprinkler | 20-Apr-19 | 15-Jun-19 |
Landscape | 20-Apr-19 | 30-Jun-19 |